138-13KV Transformer and Switchgear Replacement


 

Project Description

Our clients regional load growth demanded increased distribution system capacity and reliability plus increased operational flexibility.  The scope included the design and installation of a butler style building on slab, indoor switchgear, and 18 MVAR of bus capacitors, installation of a 3rd 62 MVA 138-13kV transformer, plus four 138kV breakers and five disconnect added to the outdoor bus configuration, and new zones of protection to be established with new relaying and SCADA control. The new 13kV circuits included the installation of a new concrete encased distribution duct banks, including 12 new manholes for the installation of the two new 13 kV circuits.  This project was planned to reduce projected overloads on two substations from 102% to 85% with increased capacity and reliability because of the newly installed reliable equipment.

Lafata-Contract-Services-Neshaminy Cable Pulling.jpg
 

 

Project Highlights

  • LCS managed and delivered this project providing Project Managers, Distribution Construction Managers, Substation Construction Managers, Substation Commissioning/Field Engineers, and Substation Project Engineers all utilizing our client’s processes and procedures.

  • The LCS Project Manager and team contracted with 12 key engineering and construction vendors and coordinated all activities from inception through design, planning, procurement, construction, and commissioning to successfully deliver this project with zero safety events.

 
 

 

OTHER ELECTRIC DISTRIBUTION PROJECTS

TakeThree Studio

Creative Duo & Design Studio✌🏼


💡We help brands tell their stories
⚡️Branding, Strategy & Websites
🚀1:1 Mentorship & Creative Consulting

https://www.takethreestudio.com
Previous
Previous

Transformational Reliability Improvement Program (TRIP)

Next
Next

34KV Ring Bus to Switchgear